Bucklers Mead Academy - Sports Hall & Changing Refurbishment

Bucklers Mead Academy - Sports Hall & Changing Refurbishment

Jones Building Group has completed the refurbishment of an existing Sports hall, Changing Rooms, and Office area, and the construction of Changing Rooms and Classrooms for Bucklers Mead Academy.

The project was fixed at 34 weeks between May 2012 and January 2013. Local         Sub-Contractors and suppliers were used, and great care was taken to ensure all materials used matched existing materials use on the site. The project was over budget due to the unforeseen presence of underground services: diversion works were carried out at short notice to avoid excessive delays.

Regular monthly meetings were held to discuss design, programme, and progress. The construction Phase Health and Safety Plan was drawn up to comply with the requirements of the Academy in respect of noise, disruption, dust and the delay of day-to-day activities.