Jones Building Group has completed an extension for a new atrium for Bucklers Mead Academy.; including improving the main entrance with two new interview rooms, and a large vestibule area.

All works were planned to be started as close to 15th July as possible to co-inside with exams and expected planning approval, and for the work to be completed by the October half term before term time commences, as well as the segregation and protection of staff, pupils and visitors.

The contract was fixed at 15 weeks between July and October 2013, and it was agreed that the build would be carried out in one phase. The initial price was over budget: the design team and Jones carried out valued engineering to save £20k and there were also challenges with the underground sewer diversion. 